In this section
Knowledge Hub / The Network / Wastewater / Wastewater treatment plants / Moa Point Wastewater Treatment Plant

Moa Point Wastewater Treatment Plant

At the Moa Point Treatment Plant, sewage travels through a series of screens, tanks, bioreactors, clarifiers and ultraviolet treatments before being discharged as liquid into Cook Strait.

It was granted new consents on 11 May 2009. These consents will continue for 25 years (expire 11 May 2034).

In general, the consents allow WCC:

  • to continuously discharge up to 260,000 cubic meters per day of treated and disinfected wastewater into the coastal marine area via an existing submarine outfall,
  • to discharge up to 4500 litres per second of mixed disinfected, treated and milli-screened wastewater to the coastal marine area during and/or immediately after heavy rainfall, when the quantity of wastewater arriving at the Moa Point Wastewater Treatment Plant exceeds 3000 litres per second,
  • to occupy the foreshore and seabed of the coastal marine area with an existing submarine outfall pipeline,
  • to continuously discharge contaminants (including odour) to air from the Moa Point Wastewater Treatment Plant ventilation system.

Resource consents

Resource consent reports

Plant performance



Current Status:
 Non-compliant 
Period: May 2024

Commentary:

The plant remains non-compliant for suspended solids, faecal coliforms and Biochemical Oxygen Demand (BOD) (all 90-day, 90th percentile limits). Steps to fix this are being undertaken, however, breakdowns at the plant are impacting a return to compliance. The return to three operating clarifiers in July is expected to improve treatment processes. 

Discharges

On May 1st, untreated wastewater was released into Tarakena Bay because of heavy rain and the reduced pumping capacity of the Inlet Pump Station (IPS) due to the IPS renewal project. 

Odour:

There were 16 odour complaints relating to the Southern Landfill site and Careys Gully Sludge Dewatering plant. None were assessed to be offensive and objectionable by GWRC.


Items of significance:

Clarifier #2 Renewal Project

The mechanical repairs to the clarifier, including corrosion protection of the structural components has progressed well and is expected to be completed early June. The next step is to replace the major mechanical components including the main bearing. The clarifier should be back in operation by July 12th.

Inlet Pump Station (IPS) Project

The two new riser pipes have been successfully installed and the wet well is back in service.  Four out of 10 riser pipes still need to be  replaced and this is planned for early 2025.

Advisory Notice issued

Greater Wellington Regional Council issued an advisory notice to Wellington Water for the sludge carry over discharge via the long outfall pipeline that occurred on 23 January.

Public meeting resources